: news

| < 2010 | jan | feb | mar | apr | may | jun | jul | aug | sep

HPP MOSTARSKO BLATO in operation since 13/05/2010


KONČAR – KET and its partners has put into operation HPP Mostarsko blato, rated power 2 x 35.3 MVA.


The whole project was coordinated by KONČAR - KET as the leader of the Consortium "Mostar", consisting of KONČAR –KET and EnergoControl Zagreb.

Power station equipment consists of two generators, 35.3 MVA each, generator voltage installations, segregated phase buses, two power transformers 35.3 MVA each, control and protection equipment, main and auxiliary low voltage equipment, switchgear 20 kV, and high voltage outdoor switchgear 110 kV.


Končar Group Companies that participated in the project are: Končar - Generators and Motors, Končar – Electronics and Informatics, Končar - Metal Structures, Končar - Switchgear, Končar – Distribution and Special Transformers and Končar - Electrical Engineering Institute.

Collaborators on the project along with the company EnergoControl Zagreb, as a member of the consortium, were Litostroj Power from Slovenia, Siemens Zagreb and Spin from Posušje, Bosnia and Herzegovina.